In this fast-changing world, the requirements for jobs and talents are higher, and if people want to find a job with high salary they must boost varied skills which not only include the good health but also the working abilities. The Construction-Manager exam torrent is compiled by the experienced professionals and of great value. You can master them fast and easily. We provide varied versions for you to choose and you can find the most suitable version of Construction-Manager Exam Materials. So it is convenient for the learners to master the Certified Construction Manager questions torrent and pass the exam in a short time.
ActualTorrent to provide you with the real exam environment to help you find the real CMAA Construction-Manager exam preparation process. If you are a beginner or want to improve your professional skills, ActualTorrent CMAA Construction-Manager will help you, let you approached you desire step by step. If you have any questions on the exam question and answers, we will help you solve it. Within a year, we will offer free update.
>> Latest Construction-Manager Dumps Book <<
Selecting ActualTorrent can 100% help you pass the exam. According to CMAA Construction-Manager test subjects' changing, we will continue to update our training materials and will provide the latest exam content. ActualTorrent can provide a free 24-hour online customer service for you. If you do not pass CMAA Certification Construction-Manager Exam, we will full refund to you.
NEW QUESTION # 58
As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?
Answer: B
Explanation:
Value Engineering (VE) is intended to improve value by optimizing the relationship between function, cost, and life-cycle performance. The CM would emphasize that VE is amulti-discipline reviewof project functions and alternate design solutions to reduce cost without sacrificing essential performance. In a proper VE workshop, participants from multiple disciplines review function, identify alternatives, and propose changes.
The incorrect choices are:
A is wrong because life cycle and maintenance costsshouldbe considered - VE should look beyond initial cost to long-term costs.
C is simplistic: while scope reduction is one possible result, VE is not merely scope cutting but exploring alternatives to maintain functionality at lower cost.
D is incorrect, because interfacing with the design-build team is essential - VE must involve the DB team to ensure proposed changes are implementable and integrated.
NEW QUESTION # 59
Industry best practice is to conduct a pre-bid conference. The intent of the pre-bid conference is to
Answer: B
Explanation:
TheCMAA Construction Management Standards of Practice (SOP)identifies thepre-bid (pre-proposal) conferenceas a key element of the procurement process. Its purpose is to clarify thescope of work, contract requirements, and bid instructionsbefore bids are submitted.
CMAA states:
"A pre-bid conference provides prospective bidders with an opportunity to review the contract requirements, clarify ambiguities, and receive consistent responses to questions regarding scope, schedule, and procedures." By ensuring that all bidders receive the same information, the CM helps promote fair competition, minimize post-award claims, and reduce misunderstandings about scope-thereby indirectly helping to mitigate change orders and delays. However, theprimary intentis toresolve any questions about contract requirements and scope of work.
Option B describes a benefit, but not the immediate intent; Option A concerns site investigation, which is typically handled in separate pre-bid site visits; Option C is contrary to public procurement policy.
Therefore, the correct answer isD.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, Chapter 5 - Contract Administration, Section:
"Procurement and Pre-Bid Activities."
CMAA CM Study Guide, Contract Administration Domain, Objective 5.2: "Conduct pre-bid and pre- construction conferences to clarify contract requirements."
NEW QUESTION # 60
A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month
10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
Which statement most accurately portrays program status?
Answer: B
Explanation:
Per theCMAA Cost and Time Managementprinciples, progress evaluation is based onearned valuerelative to planned progress.
Planned progress at month 10 = 10 stores/month × 10 months =100 stores planned.
Actual progress =100 stores completed, representing 10/12 (#83%) of total scope.
Thus, the project ison schedule by units completed, but the total duration is 12 months, and the total value earned is $1.1M of $1.2M =91.7% of total cost value, which proportionally exceeds the planned percentage for 10/12 months (#83%).
Therefore, while the progress in number of stores matches schedule, theearned value ($1.1M)exceeds the proportional planned value, which can indicate front-loading or over-reported cost progress. Since month 10 implies two months remaining (20 stores left), to stay on plan they should be at approximately $1.0M earned value. The pay application exceeds this.
However, given the full comparison,the schedule is behind overall program completion(as 100/120 stores =
83%), but thepayment reflects that same completion percentage accurately, not inflated. Thus, optionC ("Behind schedule, pay application accurately reflects percentage complete") is the correct interpretation.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, Chapter 3 - Cost Management and Chapter 4 - Time Management.
CMAA CM Study Guide, Cost Management Domain, Objective 3.4: "Evaluate project cost and earned value."
NEW QUESTION # 61
The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?
Answer: D
Explanation:
According to theCMAA Construction Management Standards of Practice (SOP), withinContract AdministrationandProject Closeout, theConstruction Manager (CM)is responsible for coordinating all activities related to project turnover, including ensuring that spare parts, warranties, guarantees, and maintenance manuals are transferred properly to the owner.
CMAA states:
"The Construction Manager shall coordinate and verify that all deliverables required by the contract, including spare parts, warranties, record drawings, and operation and maintenance manuals, are received, reviewed, and transmitted to the Owner prior to project closeout." While thecontractoris responsible forprovidingthe spare parts and warranties per the contract, theCMis explicitly tasked withcoordinatingthe transfer and verifying completion. Regulatory agencies do not perform this function, commissioning authorities (CxA) focus on system performance, and the designer's role is typically limited to verification or approval of submittals-not physical coordination.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Contract Administration, Section: "Project Closeout and Turnover." CMAA CM Study Guide, Contract Administration Domain, Objective 5.6: "Coordinate turnover, documentation, and warranties."
NEW QUESTION # 62
The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non- conformance report was issued. The engineer of record's repair detail showed to cut and remove the dislodged waterstop sections. The authority/agency re-approved the detail as the waterstop is part of a secondary waterproofing system and the primary system was deemed sufficient. The contractor did not comply with the detail and placed the concrete roof slab over the dislodged material. In this scenario, which of the following options represents the BEST course of action?
Answer: D
Explanation:
PerCMAA Standards of Practice (Chapter 5 - Quality Management and Chapter 6 - Contract Administration), when non-conforming work is discovered and the contractor fails to comply with approved corrective instructions, the appropriate procedure is for thecontractor to submit a proposed corrective action or repair detailfor review and approval by theengineer of recordand theowner.
The SOP emphasizes:
"The contractor is responsible for proposing a corrective action for nonconforming work. The CM shall ensure the proposal is reviewed and approved by the design professional and owner prior to implementation." Accepting the condition as-is (Option C) would be improper without formal approval, and unilateral removal or demolition (Options B or D) should only occur after the approved corrective process is completed.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Quality Management, Section "Nonconforming Work and Corrective Action." CMAA CM Study Guide, Quality Management Domain, Objective 5.4: "Coordinate the review and approval of corrective actions for nonconforming work."
NEW QUESTION # 63
......
The Certified Construction Manager (CCM) (Construction-Manager) web-based practice questions carry the above-mentioned notable features of the desktop-based software. This version of ActualTorrent's Certified Construction Manager (CCM) (Construction-Manager) practice questions works on Mac, Linux, Android, iOS, and Windows. Our customer does not need troubling plugins or software installations to attempt the web-based CMAA in Construction-Manager Practice Questions. Another benefit is that our CMAA Construction-Manager online mock test can be taken via all browsers, including Chrome, MS Edge, Internet Explorer, Safari, Opera, and Firefox.
Construction-Manager Reliable Braindumps Ppt: https://www.actualtorrent.com/Construction-Manager-questions-answers.html
It is not an easy task to pass the Construction-Manager Reliable Braindumps Ppt - Certified Construction Manager (CCM) certification exam on the first attempt, but now ActualTorrent Construction-Manager Reliable Braindumps Ppt is here to help, CMAA Latest Construction-Manager Dumps Book Believe us that we can bring you the service of high quality and make you satisfied, We have online and offline service, and the staff possess the professional knowledge for Construction-Manager exam dumps, if you have any questions, you can have a conversation with us, CMAA Latest Construction-Manager Dumps Book Design and implementation of Serverless solutions is an additional thing that is covered in this book.
This silent killer, if left untreated, can lead to coronary Construction-Manager Free Practice disease, renal disease, strokes, and other life-threatening illnesses, They are: Compatibility between versions.
It is not an easy task to pass the Certified Construction Manager (CCM) certification exam on the Reliable Construction-Manager Exam Tips first attempt, but now ActualTorrent is here to help, Believe us that we can bring you the service of high quality and make you satisfied.
We have online and offline service, and the staff possess the professional knowledge for Construction-Manager Exam Dumps, if you have any questions, you can have a conversation with us.
Design and implementation of Serverless solutions is an additional thing that Construction-Manager is covered in this book, Our PDF files can be easily downloaded and accessed on various devices, including PCs, laptops, Macs, tablets, and smartphones.
(2025) Elite Global Internships. All rights reserved